Alberta Electric System Operator
System Co-ordination Plan
2025-06-19 to 2025-06-27
Approved Outages

Previous Version
Download CSV

From To Owner Type Element Scheduled Activity Date/Time Comments Interconnection
05-Oct-18 08:00 30-Aug-25 16:00 EPCOR IO C2 (Rossdale) forced outage 2,521.33 Days
Continuous
 
24-Oct-18 01:13 30-May-27 16:00 EPCOR IO C1 (Rossdale) forced outage 3,140.62 Days
Continuous
 
27-Nov-23 08:00 01-Aug-25 16:00 ENMAX Outage 32.2TR (SS-32) 32 sub 32.2TR 8 kV bus switchgear demolition 613.29 Days
Continuous
 
26-Jul-24 10:00 31-Jul-26 16:00 ATCO Outage 826s 504R (826s Marguerite Lake) emergency removal to replace failed 502R @834S 735.25 Days
Continuous
 
23-Aug-24 13:45 30-Jun-26 14:29 ALTALINK Outage 157s C1 (157s Lac La Biche) forced outage 676.03 Days
Continuous
 
03-Jan-25 07:00 27-Jun-25 17:00 EPCOR TE 805s Protection & Control (805s Jasper), 805s RTU/SCADA (805s Jasper) protection blocking for P&C maintenance at Jasper 175.38 Days
Continuous
 
24-Jan-25 00:00 31-Dec-25 16:00 ALTALINK Outage 74s C3 (74s Janet) forced outage 341.67 Days
Continuous
 
10-Feb-25 00:00 23-Dec-25 23:00 ATCO, ALTALINK IO 840s McNeill Station, 830L (562s Cypress - 840s McNeill Station), 840s 701T (840s McNeill Station), 840s 901T (840s McNeill Station) available for emergency use only 316.96 Days
Continuous
AB-SK
11-Feb-25 10:00 23-Jun-25 16:00 ATCO TE 940s Protection & Control (940s Beartrap) relay testing 132.21 Days
Continuous
 
11-Mar-25 00:00 31-Dec-25 16:00 ALTALINK Outage 377s C1 (377s AML Hardisty) forced outage 295.71 Days
Continuous
 
18-Mar-25 14:00 17-Mar-26 17:30 ALTALINK Outage 217s C1 (217s North Red Deer) cap. bank unavailable and cannot be energized due to Koncar CTs being present 364.15 Days
Daily
 
20-Mar-25 08:00 20-Mar-26 17:00 ALTALINK Outage 263s C1 (263s Strachan) forced outage 365.38 Days
Continuous
 
20-Mar-25 08:00 20-Mar-26 17:00 ALTALINK Outage 256s C1 (256s Harmattan) forced outage 365.38 Days
Continuous
 
31-Mar-25 07:00 03-Oct-25 17:00 EPCOR Outage 987s T1 (987s Clover Bar), 987s CCP7213 (987s Clover Bar), 987s CCP7214 (987s Clover Bar) Cloverbar - TX1 LCR 186.42 Days
Continuous
 
31-Mar-25 07:00 29-Aug-25 17:00 EPCOR TE 987s Protection & Control (987s Clover Bar) Cloverbar: protection blocking, 240 kV bus 3 differential for TX1 LCR duration 151.42 Days
Continuous
 
31-Mar-25 07:00 04-Jul-25 17:00 EPCOR TE Protection & Control (Woodcroft) Woodcroft: protection blocking for merging unit and protection upgrade. 95.42 Days
Continuous
 
12-May-25 08:00 29-Jun-25 16:00 ENMAX Outage 3.84L (SS-3 - SS-13), 3B138-3.84 (SS-3), 13B138-3.84 (SS-13) complete reconductoring of 3.84 line 48.33 Days
Continuous
 
14-May-25 04:01 14-Jul-25 07:30 ALTALINK Outage 799s T3 (799s Coleman) replace T3 61.15 Days
Continuous
 
14-May-25 08:00 10-Feb-26 16:00 ENMAX TE Protection & Control (SS-32) 32sub 138kV autoswitching protection outage 272.38 Days
Continuous
 
21-May-25 16:00 08-Jul-25 17:00 ATCO RB 7L20 (810s Dome Cutbank - 7L228 tap), 7L80 (740s H.R. Milner - 857s Kakwa Ridge), 7L80 (733s Simonette - 857s Kakwa Ridge) due to damaged structure on 7L20 48.04 Days
Continuous
 
25-May-25 07:00 01-Aug-25 17:00 EPCOR Outage 987s GT2 (987s Clover Bar) maintenance 68.42 Days
Continuous
 
29-May-25 17:31 30-Jun-25 00:00 BHE Canada Outage 120s C1 (120s Picture Butte) forced outage 31.27 Days
Continuous
AB-MATL
01-Jun-25 14:44 27-Jun-25 17:00 ATCO Outage 7L94 (827s Cranberry Lake - 878s Kidney Lake) forced outage due to wildfire 26.09 Days
Continuous
 
02-Jun-25 07:00 27-Jun-25 17:00 EPCOR Outage 557s T1 (557s Castle Downs) S/S Tx1 bay outage 25.42 Days
Continuous
 
02-Jun-25 09:00 24-Jun-25 20:00 SUNCOR TE 29EDD-94 RTU/SCADA (29EDD-94 Voyageur), Suncor PMU fiber circuit testing at 29EDD-94 to investigate/fix the issues on PMU data 22.46 Days
Continuous
 
02-Jun-25 10:00 20-Jun-25 17:30 ATCO TE 813s Protection & Control (813s Little Smoky), 813s RTU/SCADA (813s Little Smoky) update DFR for AESO streaming

, replace 700PT disconnects
, wire 700PTY2 to DFR2
, replace 704PT disconnects
, wire 704PTY2 to DFR2
and install new satellite clock

- SCADA updates
18.31 Days
Continuous
 
08-Jun-25 15:00 25-Nov-25 15:30 ALTALINK Outage 397s 864W (397s Benbow) new 864L line construction, new 397s48 (VT6) install 170.06 Days
Continuous
 
08-Jun-25 15:00 25-Jun-25 07:59 ALTALINK Outage 355s T1 (355s Chevron Knight), 355s T2 (355s Chevron Knight) maintenance, salvage 4.16kV cable bus associated with T2 16.71 Days
Continuous
 
09-Jun-25 07:00 20-Jun-25 17:00 EPCOR Outage 657s T2 (657s Summerside) Summerside - TX2 DGA LCR 11.42 Days
Continuous
 
09-Jun-25 07:00 27-Jun-25 17:00 EPCOR Outage 52s T1 (52s East Industrial), 52s E2401 (52s East Industrial) transformer T1 protection upgrade cutovers 18.42 Days
Continuous
 
09-Jun-25 07:00 20-Jun-25 17:00 EPCOR Outage T3 (Woodcroft), W722 (Woodcroft) T3 zone protection upgrade cutovers 11.42 Days
Continuous
 
09-Jun-25 07:00 01-Aug-25 17:00 EPCOR TE 330p Protection & Control (330p Genesee) 138/500 kV protection blocking for relay maintenance 53.42 Days
Continuous
 
09-Jun-25 07:00 15-Aug-25 17:00 EPCOR TE Protection & Control (Poundmaker) protection blocking for relay maintenance 67.42 Days
Continuous
 
09-Jun-25 13:30 30-Jun-25 18:00 ATCO Outage 716s 701C (716s Lloydminster) emergency maintenance 21.19 Days
Continuous
 
10-Jun-25 10:00 19-Jun-25 19:00 ALTALINK Outage 1012L (326s Murray Lake - 516s Forty Mile) complete the bus tie scope at the substation 9.38 Days
Continuous
 
12-Jun-25 08:00 23-Jun-25 17:00 ATCO TE 808s Protection & Control (808s Procter & Gamble) 7L13 21B relay replacement 11.38 Days
Continuous
 
12-Jun-25 08:00 23-Jun-25 17:00 ATCO TE 845s Protection & Control (845s Big Mountain), 845s RTU/SCADA (845s Big Mountain) 7L13 21B relay replacement and RTU changes required to incorporate new 21B relay 11.38 Days
Continuous
 
13-Jun-25 17:00 11-Feb-26 17:00 EPCOR Outage T3 (Rossdale) Rossdale - TX3 LCR 243.04 Days
Continuous
 
13-Jun-25 20:01 25-Jun-25 20:00 SUNCOR Outage 29PL6-2 (30EDD-1 - 29EDD-55), 30EDD-1 622T (30EDD-1), 30EDD-1 626 (30EDD-1), 30EDD-1 625 (30EDD-1), 30EDD-1 624 (30EDD-1), 30EDD-1 622TD (30EDD-1), 30EDD-1 29PL6-2CS (30EDD-1) 5 year preventive maintenance 12 Days
Continuous
 
16-Jun-25 07:00 20-Jun-25 17:00 EPCOR Outage 1164L (816s Petrolia - EP Riverview), RW2402 (EP Riverview), RW2401 (EP Riverview), 816s P2403 (816s Petrolia), 816s P2404 (816s Petrolia) 1164L zone doble and relay maintenance 4.42 Days
Continuous
 
16-Jun-25 07:00 20-Jun-25 17:00 EPCOR Outage 72RV2 (EP 511s Victoria - Rossdale), RV728 (Rossdale), EP 511s V721 (EP 511s Victoria), EP 511s V729 (EP 511s Victoria), EP 511s VDS1 (EP 511s Victoria) doble and disconnect maintenance 4.42 Days
Continuous
 
16-Jun-25 07:00 21-Jun-25 17:00 EPCOR Outage 746AL (524s Owens Corning - 746L tap), 524s 6 (524s Owens Corning), 524s T1 (524s Owens Corning) TX1 bushing replacement and 746AL corona ring Install 5.42 Days
Continuous
 
16-Jun-25 07:00 23-Jun-25 18:00 ATCO, CNRL Outage 859s 702T (859s Primrose) 702T full testing including protections 7.46 Days
Continuous
 
16-Jun-25 07:00 22-Jun-25 19:00 ATCO RB 9L20 (755s Cordel - 766s Nevis) to complete stringing activities on CETO project adjacent to 9L20 6.5 Days
Daily
 
16-Jun-25 07:00 20-Jun-25 16:00 ALTALINK Outage 133s T1 (133s Stelco Edmonton), 133s T2 (133s Stelco Edmonton), 133s 1 (133s Stelco Edmonton), 133s 2 (133s Stelco Edmonton) install grounds 4.38 Days
Continuous
 
16-Jun-25 07:30 19-Jun-25 17:30 ALTALINK RB 799L (235s Entwistle - 443s South Mayerthorpe), 799L (77s Sagitawah - 443s South Mayerthorpe) proximity RB for 799L rebuild (Str 858-889) 3.42 Days
Daily
 
16-Jun-25 07:30 20-Jun-25 17:30 ALTALINK RB 514L (396s Pincher Creek - 514BL tap), 514L (513s Lundbreck - 514BL tap) south crew will be doing component replacement on 514L (Str 16-186)& (Str 452-453) Live Line 4.42 Days
Daily
 
16-Jun-25 08:00 20-Jun-25 17:00 ALTALINK TE 799s RTU/SCADA (799s Coleman) supervisory outages required for addition and testing of alarms/controls associated with new T3 and associated protection upgrade 4.38 Days
Daily
 
16-Jun-25 08:00 04-Jul-25 16:00 ENMAX Outage 31.1C (SS-31) capacitor bank switcher replacement, grounding improvements 18.33 Days
Continuous
 
16-Jun-25 08:00 20-Jun-25 17:00 ALTALINK TE 799s Protection & Control (799s Coleman) circuit cutover and testing 4.38 Days
Daily
 
16-Jun-25 08:00 19-Jun-25 16:00 ATCO RB 7L51 (788s Hotchkiss - 927s Buchanan Creek), 7L51 (ATC 793s West Peace River - 927s Buchanan Creek) 7L51 walk up and climbing inspection 3.33 Days
Continuous
 
16-Jun-25 08:00 19-Jun-25 17:00 ALTALINK TE 151s RTU/SCADA (151s Strathmore) to complete trouble shoot of IED alarm and removal of UF from 25kV lines, possible RTU config changes required 3.38 Days
Daily
 
16-Jun-25 08:00 19-Jun-25 18:00 ENMAX Outage 43.2TR (SS-43) tap changer inspection, reversing switch check, oil sampling 3.42 Days
Continuous
 
16-Jun-25 08:00 01-Aug-25 17:00 ATCO TE 808s Protection & Control (808s Procter & Gamble), 808s RTU/SCADA (808s Procter & Gamble) SCADA upgrade at 808S. Protection and hardwired IO on-site will need to be cut-over to new SCADA system and tested 46.38 Days
Continuous
 
16-Jun-25 08:00 19-Jun-25 16:00 ENMAX Outage 27.2TR (SS-27) transformer maintenance and testing 3.33 Days
Continuous
 
16-Jun-25 08:00 19-Jun-25 17:30 ALTALINK, ALPAC TE 282s Protection & Control (282s Grassland (Alpac)), 405s Protection & Control (405s Waupisoo) facilitate 9900R radio outages 3.4 Days
Daily
 
16-Jun-25 09:00 25-Jun-25 17:00 BCH Outage 5L77 (BCH Ashton Creek - BCH Revelstoke G.S.) replace flashed and broken insulators


9.33 Days
Continuous
AB-BC
16-Jun-25 10:00 20-Jun-25 17:30 ATCO Outage 959s 901T (959s Lanfine) transformer class 1 major testing, tap changer class 1 testing and qualitrol ITM/ETM settings updates 4.31 Days
Continuous
 
16-Jun-25 10:00 20-Jun-25 17:30 ATCO TE 959s Protection & Control (959s Lanfine), 959s RTU/SCADA (959s Lanfine) updates RTU 4.31 Days
Continuous
 
16-Jun-25 11:00 19-Jun-25 17:00 ALTALINK TE 310p RTU/SCADA (310p Sundance) update RTU database 3.25 Days
Daily
 
16-Jun-25 11:30 20-Jun-25 16:30 ALTALINK Outage 650s SVC (650s Hansman Lake), 650s T3 (650s Hansman Lake), 650s 252 (650s Hansman Lake), 650s 352 (650s Hansman Lake), 650s 489 (650s Hansman Lake) maintenance on SVC and breaker testing 4.21 Days
Continuous
 
16-Jun-25 12:00 20-Jun-25 16:00 ATCO Outage 885s 902T (885s McMillan), 885s 501R (885s McMillan) replace 1 single phase reactor in 501R,
902T major and tap changer refurbishment
4.17 Days
Continuous
 
16-Jun-25 12:00 09-Jul-25 17:00 ATCO TE 845s Protection & Control (845s Big Mountain) block 50BF/702 relay as required to commission new connections associated with 21A/7L13 and 21B/7L13 relay replacements 23.21 Days
Continuous
 
16-Jun-25 12:00 09-Jul-25 17:00 ATCO TE 845s Protection & Control (845s Big Mountain) block 50BF/703 relay as required to commission new connections associated with 21A/7L13 and 21B/7L13 relay replacements 23.21 Days
Continuous
 
16-Jun-25 12:00 23-Jun-25 17:00 ATCO TE 845s Protection & Control (845s Big Mountain) block 21B/7L45 in order to perform 702PTY2 voltage injections needed for 21B/7L13 relay replacement 7.21 Days
Continuous
 
16-Jun-25 12:00 23-Jun-25 17:00 ATCO TE 845s Protection & Control (845s Big Mountain) block 21B/7L228 in order to perform 702PTY2 voltage injections needed for 21B/7L13 relay replacement 7.21 Days
Continuous
 
17-Jun-25 08:00 20-Jun-25 18:00 ATCO TE ATCO RTU/SCADA 6500S RTU - cutover from ATCO Electric control center to URICA control center, update and test new RTAC configurations 3.42 Days
Continuous
 
17-Jun-25 08:00 19-Jun-25 17:00 ALTALINK TE 310p Protection & Control (310p Sundance) DSP card replacement/standard maintenance 2.38 Days
Daily
 
17-Jun-25 09:00 21-Jun-25 09:00 ALTALINK Outage 163s T1 (163s Amoco Empress) unbolt/re-connect cabling from Altalink bus into plains substation for cable testing 4 Days
Continuous
 
17-Jun-25 09:00 20-Jun-25 20:00 SUNCOR TE 29EDD-34 29-652-10202 (29EDD-34), 29EDD-34 Protection & Control (29EDD-34) test relay B-51G,P120, - 29PL6-38 - Block 7 Relay 450037252
3.46 Days
Continuous
 
17-Jun-25 10:00 19-Jun-25 17:00 ATCO TE 898s Heart Lake RTU/SCADA CCTV installation requires the addition of alarms and data path for camera footage 2.29 Days
Continuous
 
18-Jun-25 07:00 19-Jun-25 17:00 ALTALINK, MEGEC TE 762s Protection & Control (762s Conklin) card replacement on 762s B87/21/971L (971L) 1.42 Days
Daily
 
18-Jun-25 07:00 19-Jun-25 15:30 ALTALINK, MEGEC TE 762s RTU/SCADA (762s Conklin) relay card replacement. 1.35 Days
Daily
 
18-Jun-25 08:00 20-Jun-25 18:00 ATCO TE ATCO RTU/SCADA update and test new RTAC configurations 2.42 Days
Continuous
 
18-Jun-25 08:00 19-Jun-25 16:00 ENMAX Outage 22.81L (SS-22 - SS-39), 39B138-22.81 (SS-39), 22B138-22.81 (SS-22) breaker maintenance 1.33 Days
Continuous
 
18-Jun-25 08:00 20-Jun-25 17:00 ALTALINK Outage 786L (799s Coleman - BCH Natal) move fiber run to accommodate construction 2.38 Days
Continuous
AB-BC
18-Jun-25 08:00 20-Jun-25 17:00 ALTALINK TE AltaLink Telecom Equipment, 799s Coleman move fiber run 2.38 Days
Continuous
 
18-Jun-25 08:00 19-Jun-25 17:00 ALTALINK TE 154s Protection & Control (154s Black Spruce) card replacement 1.38 Days
Daily
 
18-Jun-25 08:00 19-Jun-25 17:00 ALTALINK TE 154s RTU/SCADA (154s Black Spruce) relay card replacement. 1.38 Days
Daily
 
18-Jun-25 08:30 20-Jun-25 17:00 ALTALINK TE 698s Protection & Control (698s Jackfish) standard relay maintenance. 2.35 Days
Daily
 
18-Jun-25 14:00 26-Jun-25 13:00 BCH Outage 5L72 (BCH Mica G.S. - BCH Nicola) MCA 5CVT23 PM
7.96 Days
Continuous
 
19-Jun-25 07:00 20-Jun-25 18:00 ALTALINK, ENBRIDGE Outage 703L (213s Hughenden - 703BL tap), 213s 703 (213s Hughenden), 329s HRT-S2 (329s Hrt Express) replace arms and insulators on structure 39. replace structure 77. repair woodpecker damage on structure 78. 1.46 Days
Daily
 
19-Jun-25 07:00 19-Jun-25 17:00 EPCOR Outage GT3 (Garneau), T3 (Garneau) Garneau: TX3 SF6 pressure alarm repair 10 Hours
Continuous
 
19-Jun-25 08:00 20-Jun-25 19:00 ATCO Outage 845s 703 (845s Big Mountain) protection upgrade 21A & 21B relays 7L13.
CT testing, breaker testing
1.46 Days
Continuous
 
19-Jun-25 08:00 20-Jun-25 19:00 ATCO Outage 808s 702T (808s Procter & Gamble), 808s 702 (808s Procter & Gamble) 7L13 relay replacement.
CT testing, breaker testing
1.46 Days
Continuous
 
19-Jun-25 08:00 19-Jun-25 17:00 ALTALINK TE AltaLink Telecom Equipment upgrade software affecting 9900R-405s radio to resolve sync lock alarms. all supervisory circuits re-reroute in 50ms or less. 9 Hours
Daily
 
19-Jun-25 08:00 24-Jun-25 16:00 SUNCOR Outage 635EDD-1000 635PK-1001 (635EDD-1000) 635EDD-1001 144kV diameter 3 equipment maintenance 5.33 Days
Continuous
 
19-Jun-25 08:00 19-Jun-25 16:00 ALTALINK TE 257s RTU/SCADA (257s Hull) RTU outages required to upgrade the configuration. regarding the fault reporting project. 8 Hours
Daily
 
19-Jun-25 08:00 19-Jun-25 14:00 ALTALINK Outage 421s T1 (421s Hays), 421s 2 (421s Hays) repair (tighten) 421sT1 H3 bushing as needed. It is approximately 30 degrees hot. 6 Hours
Daily
 
19-Jun-25 08:00 19-Jun-25 17:00 ENMAX, ALTALINK RB 1003L (74s Janet - SS-25) Altalink outage. barehand training crew will be doing a hot inline splice at 1003L16A 9 Hours
Continuous
 
19-Jun-25 08:00 19-Jun-25 17:00 ENMAX, ALTALINK RB 1003L (74s Janet - SS-25) barehand training crew will be doing a hot inline splice at Str 15-16 9 Hours
Daily
 
19-Jun-25 08:00 19-Jun-25 17:00 ALTALINK TE 391s Protection & Control (391s Balzac) PRC maintenance 9 Hours
Daily
 
19-Jun-25 08:00 19-Jun-25 17:00 ALTALINK TE 257s RTU/SCADA (257s Hull) configuration update on RTU required for future Fault reporting project. 9 Hours
Daily
 
19-Jun-25 08:00 19-Jun-25 17:00 ENMAX, ALTALINK RB 985L (74s Janet - SS-25) Altalink outage. proximity to str 16 during 1003L RB 9 Hours
Continuous
 
19-Jun-25 08:00 19-Jun-25 17:00 ENMAX, ALTALINK RB 985L (74s Janet - SS-25) proximity to str 16 during 1003L RB. 9 Hours
Daily
 
19-Jun-25 08:30 19-Jun-25 14:00 Lethbridge TE 241s Protection & Control (241s Uplands) cutover SCADA points from SURVALENT Scout to SEL RTAC Relay 5.5 Hours
Continuous
 
19-Jun-25 09:00 19-Jun-25 17:00 ATCO TE ATCO Telecom Equipment, 804s RTU/SCADA (804s Wintering Hills) LOW BES firewall Install - outage to local network & SCADA communications. 8 Hours
Continuous
 
20-Jun-25 07:30 22-Jun-25 17:30 ALTALINK RB 1201L (520s Bennett - BCH Cranbrook) barehand training crew will be replacing insulation and jumpers at STRs 2, 101 & 103 2.42 Days
Daily
 
20-Jun-25 08:00 20-Jun-25 16:00 ENMAX Outage 162B138-RB81 (SS-162) hv breaker maintenance - 162B138-RB81, breaker dashpot checks 8 Hours
Continuous
 
20-Jun-25 08:00 20-Jun-25 16:00 ENMAX Outage 13.60L (SS-13 - SS-27), 27.2TR (SS-27) Make repairs to damaged 27MD69-27.2TR 8 Hours
Continuous
 
21-Jun-25 08:00 21-Jun-25 18:00 ENMAX Outage 2.83L (SS-5 - 2.83L tap), 2.83L (SS-2 - 2.83L tap), 2.83L (SS-13 - 2.83L tap), 3.84L (SS-3 - SS-13), 13.1TR (SS-13), 13.3TR (SS-13), 13B138-2.83 (SS-13), 13B138-3.84 (SS-13), 5B138-2.83 (SS-5), 3B138-3.84 (SS-3), SW83 (SS-13), 13MD138-13.1TR (SS-13), 13MD138-13.3TR (SS-13), 2MD138-2.83 (SS-2) oil sampling - 13.3-TC, MT, summer substation washing 10 Hours
Continuous
 
21-Jun-25 08:00 08-Jul-25 16:00 Syncrude, ATCO Outage RL1 (848s Ruth Lake - D05), T2 (D05 Syncrude), D05 517 (D05), D05 516 (D05), D05 513 (D05), D05 78 (D05), D05 517B (D05), D05 516A (D05), D05 516B (D05), D05 513A (D05), D05 513B (D05), D05 509 (D05), D05 78A (D05), 848s RL-1D1 (848s Ruth Lake) 6-year 260 kV and 72 kV preventive maintenance 17.33 Days
Continuous
 
22-Jun-25 08:00 22-Jun-25 12:00 ENMAX Outage 21.4TR (SS-21), 21B69-21.4TR (SS-21) HV breaker SF6 gas sample - 21B69-21.4TR 4 Hours
Continuous
 
22-Jun-25 08:00 22-Jun-25 17:00 ENMAX, ALTALINK RB 1003L (74s Janet - SS-25) Altalink outage - bare hand training, hot inline splice at 1003L16A 9 Hours
Continuous
 
22-Jun-25 08:00 22-Jun-25 17:00 ENMAX, ALTALINK RB 1003L (74s Janet - SS-25) bare hand training, hot inline splice at str 15-16 9 Hours
Daily
 
22-Jun-25 08:00 22-Jun-25 17:00 ENMAX, ALTALINK RB 985L (74s Janet - SS-25) Altalink outage - proximity to str 16 during 1003L RB 9 Hours
Continuous
 
22-Jun-25 08:00 22-Jun-25 17:00 ENMAX, ALTALINK RB 985L (74s Janet - SS-25) proximity to str 16 during 1003L RB 9 Hours
Daily
 
22-Jun-25 09:00 24-Jun-25 14:00 ENMAX Outage 31.2TR (SS-31) grounding improvements ,install new surge arrestor insulator supports, and grounding 2.21 Days
Continuous
 
22-Jun-25 12:00 22-Jun-25 16:00 ENMAX, ALTALINK Outage 28.80L (42s Sarcee - SS-28), 28B138-28.80 (SS-28), 42s 28 (42s Sarcee) HV breaker SF6 gas sample - 28B138-28.80 4 Hours
Continuous
 
22-Jun-25 12:00 22-Jun-25 16:00 ENMAX, ALTALINK IO 28.80L (42s Sarcee - SS-28) HV breaker SF6 gas sample - 28B138-28.80 4 Hours
Daily
 
23-Jun-25 07:00 27-Jun-25 17:00 EPCOR Outage 72CH9 (987s Clover Bar - EP Hardisty), 987s CH722 (987s Clover Bar), H724 (EP Hardisty) Cloverbar: CH9 Zone Doble and CH722 Breaker Maintenance and CDS3/HDS10 Disconnect Maintenance 4.42 Days
Continuous
 
23-Jun-25 07:00 26-Jun-25 17:00 EPCOR Outage 72RV4 (EP 511s Victoria - Rossdale), EP 511s V726 (EP 511s Victoria), EP 511s V727 (EP 511s Victoria), RV726 (Rossdale) Victoria: RV4 Zone Doble and VDS15/VDS17/VDS18 Disconnect Maintenance 3.42 Days
Continuous
 
23-Jun-25 07:00 26-Jun-25 18:00 ALTALINK, VISIONREQ Outage 354s PMU (354s Summerview), 354s 138DS4 (354s Summerview) replace PMU Device with new SEL PMU. circuits. 3.46 Days
Continuous
 
23-Jun-25 07:00 26-Jun-25 17:00 ALTALINK, VISIONREQ TE 354s PMU (354s Summerview) PMU outage for replacement. No visibility via PMU. 3.42 Days
Continuous
 
23-Jun-25 07:00 26-Jun-25 18:00 ALTALINK, VISIONREQ TE 354s RTU/SCADA (354s Summerview) Supervisory / Visibility outage as requred for setup of new PMU 3.46 Days
Daily
 
23-Jun-25 07:00 27-Jun-25 17:00 EPCOR Outage RR729 (Rossdale) Rossdale: RR729 Breaker Fail Upgrade Cut Overs 4.42 Days
Continuous
 
23-Jun-25 07:00 27-Jun-25 17:30 ALTALINK TE 678s RTU/SCADA (678s Okotoks) download updated configuration, and complete points check, iInstall and commission new port server 4.44 Days
Daily
 
23-Jun-25 07:00 26-Jun-25 17:00 ALTALINK TE 227s RTU/SCADA (227s Cutting Lake) update the RTU configuration 3.42 Days
Daily
 
23-Jun-25 07:00 27-Jun-25 17:00 ALTALINK, EPCOR RB 1045L (EP 805s Jasper - 1045AL tap) 1045L: Reclose Blocking for City of Edmonton West LRT, working in proximity 4.42 Days
Continuous
 
23-Jun-25 07:00 27-Jun-25 17:30 ALTALINK, EPCOR RB 1045L (310p Sundance - 1045AL tap), 1045AL (320p Keephills - 1045L tap), 1045L (EP 805s Jasper - 1045AL tap) Reclose Blocking for City of Edmonton West LRT, working in proximity 4.44 Days
Daily
 
23-Jun-25 07:00 27-Jun-25 17:00 ALTALINK, EPCOR RB 1044L (EP 805s Jasper - 816s Petrolia) 1044L: Reclose Blocking for City of Edmonton West LRT, working in proximity 4.42 Days
Continuous
 
23-Jun-25 07:30 26-Jun-25 17:30 ALTALINK RB 799L (235s Entwistle - 443s South Mayerthorpe), 799L (77s Sagitawah - 443s South Mayerthorpe) Proximity RB for 799L rebuild (Str 731-830) 3.42 Days
Daily
 
23-Jun-25 07:30 26-Jun-25 17:30 ALTALINK RB 514L (396s Pincher Creek - 514BL tap), 514L (513s Lundbreck - 514BL tap) South Crew will be doing component replacement on 514L (Str 16-186)& (Str 452-453) Live Line 3.42 Days
Daily
 
23-Jun-25 07:30 24-Jun-25 17:30 ALTALINK RB 688AL (284s Nose Creek - 688L tap), 688L (199s East Airdrie - 688BL tap), 688BL (1055s Sollair - 688L tap), 688L (653s Summit - 688AL tap), 688L (688AL tap - 688BL tap) Barehand Training Crew will be Dead end insulation at STRs 18 and 19 Live Line 1.42 Days
Daily
 
23-Jun-25 08:00 09-Jul-25 17:00 ATCO TE 808s Protection & Control (808s Procter & Gamble) relay replacement 16.38 Days
Continuous
 
23-Jun-25 08:00 09-Jul-25 17:00 ATCO TE 845s Protection & Control (845s Big Mountain), 845s RTU/SCADA (845s Big Mountain) relay replacement 16.38 Days
Continuous
 
23-Jun-25 08:00 27-Jun-25 17:00 ALTALINK TE 799s RTU/SCADA (799s Coleman) Supervisory outages required for addition and testing of alarms/controls associated with new T3 and associated protection upgrade. Muliple 15 minute loss of visibility of 799s in the timeframe indicated. 4.38 Days
Daily
 
23-Jun-25 08:00 27-Jun-25 17:00 ALTALINK TE 799s Protection & Control (799s Coleman) circuit cutover and testing 4.38 Days
Daily
 
23-Jun-25 08:00 26-Jun-25 16:00 ATCO RB 7L43 (739s Edith Lake - 809s Louise Creek) 7L43 Walk up and climbing inspection 3.33 Days
Continuous
 
23-Jun-25 08:00 24-Jun-25 16:00 ENMAX Outage 16.63L (SS-16 - SS-36), 16B69-16.63 (SS-16) HV Breaker Maintenance - 16B69-16.63 1.33 Days
Continuous
 
23-Jun-25 08:00 24-Jun-25 17:00 ALTALINK TE 89s Protection & Control (89s Ellerslie) Remove DC from 89s909W controls to facilitate repair of 89s1140 cable. 89s909W controls will remain un-operational for the duration of the outage. 1.38 Days
Daily
 
23-Jun-25 08:00 26-Jun-25 17:30 ALTALINK TE 678s Protection & Control (678s Okotoks) SCADA upgrade project 3.4 Days
Daily
 
23-Jun-25 08:00 24-Jun-25 18:00 ENMAX Outage 38.3TR (SS-38) Tap Changer Inspection - 38.3-TC. Tap Changer Oil Filtration Maintenance. Oil Sampling MT, TC 1.42 Days
Continuous
 
23-Jun-25 08:00 26-Jun-25 16:00 ENMAX Outage 2.3TR (SS-2) Transformer Power Factor Test. Secondary Cable Test. Transformer Maintenance. Relay Fault Pressure Test. Oil Sampling MT. 3.33 Days
Continuous
 
23-Jun-25 08:00 26-Jun-25 16:00 ATCO RB 7L39 (722s Crystal Lake - 7LA39 tap), 7L39 (811s Clairmont Lake - 7LA39 tap) Walk up and climbing inspection 3.33 Days
Continuous
 
23-Jun-25 08:00 26-Jun-25 16:00 ATCO RB 7L08 (830s Carmon - 834s Wesley Creek) Walk up and climbing inspection. 3.33 Days
Continuous
 
23-Jun-25 09:00 30-Jun-25 18:00 SUNCOR TE 29EDD-34 RTU/SCADA (29EDD-34) BP (Sijin) - Upgrade Network Switch Firmware and Reboot Network Switch. 29EDD-34 Substation data visibility loss during firmware upgarde/reboot process (around 20 minutes). Substation Loss of Visibility. 7.38 Days
Continuous
 
23-Jun-25 09:00 30-Jun-25 18:00 SUNCOR TE 29EDD-1 RTU/SCADA (29EDD-1 Millennium) BP (Sijin) - Upgrade Network Switch Firmware and Reboot Network Switch. 29EDD-1 Substation and Generation data visibility loss during firmware upgarde/reboot process (around 20 minutes). 7.38 Days
Continuous
 
23-Jun-25 09:30 27-Jun-25 19:00 ATCO Outage 808s 702T (808s Procter & Gamble), 808s 702 (808s Procter & Gamble) 7L13 relay replacement,
CT testing, breaker testing
4.4 Days
Continuous
 
23-Jun-25 09:30 27-Jun-25 17:30 ATCO Outage 757s 912T (757s Battle River) TRANSFORMER CLASS1 MAJOR TESTING - 912T @ 757S
BREAKER MIN OIL HPF COMPLETE TESTING - 710 @ 757S
4.33 Days
Continuous
 
23-Jun-25 10:00 24-Jun-25 15:00 ATCO Outage 844s 701T (844s AEC Mill), 844s 701 (844s AEC Mill) oil samples and work to within LOA 29 Hours
Continuous
 
23-Jun-25 10:00 27-Jun-25 17:30 ATCO Outage 963s 901T (963s Coyote Lake), 7L128 (963s Coyote Lake - 7LA128 tap), 9L29 (946s Oakland - 963s Coyote Lake) TRANSFORMER CLASS1 TAP CHANGER - 901T @ 963S
TRANSFORMER CLASS1 MAJOR TESTING - 901T @ 963S
Qualitrol ITM/ETM Settings Updates - 901T Updates at 963s Coyote Lake
4.31 Days
Continuous
 
23-Jun-25 10:00 27-Jun-25 17:30 ATCO TE 963s RTU/SCADA (963s Coyote Lake) settings updates
4.31 Days
Continuous
 
23-Jun-25 11:00 26-Jun-25 16:00 ATCO, ALTALINK RB 9L960 (13s Deerland - 825s Whitefish Lake) Climbing inspection on 9L960 and 9L961. Crews will be climbing all towers. 3.21 Days
Continuous
 
23-Jun-25 11:00 26-Jun-25 16:00 ATCO, ALTALINK RB 9L961 (13s Deerland - 825s Whitefish Lake) Climbing inspection 3.21 Days
Continuous
 
23-Jun-25 11:00 23-Jun-25 17:00 ALTALINK TE 385s RTU/SCADA (385s Spring Coulee) UF settings removal from 112L & SCADA changes associated with removal. 15 min loss of visibility/Visibility while implementing SCADA changes. 6 Hours
Daily
 
23-Jun-25 11:00 26-Jun-25 16:00 ATCO, ALTALINK RB 9L960 (13s Deerland - 825s Whitefish Lake) 9L960 Climbing Inspection 3.21 Days
Daily
 
23-Jun-25 11:00 26-Jun-25 16:00 ATCO, ALTALINK RB 9L961 (13s Deerland - 825s Whitefish Lake) 9L961 Climbing Inspection 3.21 Days
Daily
 
23-Jun-25 11:30 26-Jun-25 18:30 ALTALINK Outage 1140L (89s Ellerslie - 289s Saunders Lake) 89s1052 Breaker maintenance + First Trip. Replace broken insulator on bus between 89s952 and 89s1052. Repair 89s1140 DC control cable. 3.29 Days
Continuous
 
23-Jun-25 11:30 26-Jun-25 18:30 ALTALINK Outage 89s T1 (89s Ellerslie) 89s T1 Doble and maintenance. Replace gas detector relay. Update Qualitrol settings. Repair oil leaks. 3.29 Days
Continuous
 
23-Jun-25 12:00 04-Jul-25 16:00 ATCO Outage 826s 901T (826s Marguerite Lake) transformer major maintenance 11.17 Days
Continuous
 
23-Jun-25 12:00 24-Jun-25 17:00 ATCO Outage 848s 404R (848s Ruth Lake), 848s 403R (848s Ruth Lake), 848s 402R (848s Ruth Lake), 848s 402 (848s Ruth Lake) PRC-005 - TRIP COIL TESTING - BREAKER 402 @ 848S 29 Hours
Continuous
 
23-Jun-25 13:30 23-Jun-25 17:00 ALTALINK TE 385s Protection & Control (385s Spring Coulee) settings changes 3.5 Hours
Daily
 
24-Jun-25 07:00 25-Jun-25 15:00 ALTALINK TE AltaLink Telecom Equipment, 121s RTU/SCADA (121s Brooks) upgrade to our firewall at 121s. 1.33 Days
Daily
 
24-Jun-25 07:00 24-Jun-25 17:00 ALTALINK TE 477s RTU/SCADA (477s Amoco West Pembina) board removal. 10 Hours
Daily
 
24-Jun-25 08:00 25-Jun-25 16:00 ENMAX IO Protection & Control (SS-37) 37sub Capacity Upgrade. Forward energize 37.3TR for 24hr soak test. Re-establish GOI for final checks. 37.3TR forward fed energizing 25kV bus June 25th. All associated protection in service. 1.33 Days
Continuous
 
24-Jun-25 08:00 26-Jun-25 18:00 ALTALINK Outage 891L1 (891L tap) SAB-1 Maintenance. 2.42 Days
Continuous
 
24-Jun-25 08:00 24-Jun-25 17:00 ALTALINK TE AltaLink Telecom Equipment investigate MPLS issue. 9 Hours
Daily
 
24-Jun-25 08:00 25-Jun-25 17:00 ALTALINK Outage 510s 2552 (510s Sunnybrook) replace grading caps 1.38 Days
Continuous
 
24-Jun-25 08:00 25-Jun-25 17:00 ALTALINK TE AltaLink Telecom Equipment install new IRU600V4 to salvage existing IRU600. 1.38 Days
Daily
 
24-Jun-25 08:00 24-Jun-25 17:00 ALTALINK TE 602s RTU/SCADA (602s Cold Creek) 2025 MPLS firmware and raw socket upgrade. 9 Hours
Daily
 
24-Jun-25 08:00 25-Jun-25 17:00 ALTALINK TE 276s Protection & Control (276s Union Carbide Prentiss), AltaLink Telecom Equipment to perform an MPLS node addition upgrade. 1.38 Days
Daily
 
24-Jun-25 08:00 25-Jun-25 16:00 ENMAX Outage 37.3TR (SS-37) forward energize 37.3TR for 24hr soak test. All associated protection in service 1.33 Days
Continuous
 
24-Jun-25 08:00 26-Jun-25 18:00 EHN, ALTALINK, ENBRIDGE Outage 226s Garden City, 891L (226s Garden City - 863L tap), 226s T1 (226s Garden City), 226s 52/T1 (226s Garden City) station maintenance 2.42 Days
Continuous
 
24-Jun-25 08:30 25-Jun-25 16:00 ATCO Outage ATC 793s 701T (ATC 793s West Peace River) testing and maintenance. 31.5 Hours
Continuous
 
24-Jun-25 08:30 24-Jun-25 14:30 ALTALINK Outage 127s C1 (127s Bruderheim), 127s 33 (127s Bruderheim) 138kV Breaker Maintenance 6 Hours
Daily
 
24-Jun-25 08:30 24-Jun-25 16:30 ALTALINK Outage 356s 152 (356s Milo) 356s152/PRC5/Maint. 8 Hours
Daily
 
24-Jun-25 08:30 24-Jun-25 12:00 ATCO RB ATC 793s 144kV Bus (ATC 793s West Peace River) Cut in Jumper J1 for 701TCS at 793s. This is in coordination with GOI 2-95443
Will need to tag breaker 701, 702, 703, 704 and 705
3.5 Hours
Continuous
 
24-Jun-25 09:00 24-Jun-25 15:00 ALTALINK Outage 618s 863X (618s Riverbend), 863L (618s Riverbend - 891L tap) insulator replacement 6 Hours
Daily
 
24-Jun-25 09:00 24-Jun-25 17:00 ATCO TE ATCO Telecom Equipment, 856s RTU/SCADA (856s Kinosis) kinosis_S-Telecom- low BES firewall install 8 Hours
Continuous
 
24-Jun-25 10:00 24-Jun-25 16:00 ATCO TE 882s RTU/SCADA (882s Triangle), ATCO Telecom Equipment telecom
need to replace the flash card or CSM card on the SAR slot B
SAR OS upgrade required and SAR reboot 6 min outage to traffic
6 Hours
Continuous
 
24-Jun-25 15:30 25-Jun-25 16:30 ATCO Outage 844s 702T (844s AEC Mill), 844s 402 (844s AEC Mill) oil samples and work to within LOA. 25 Hours
Continuous
 
25-Jun-25 07:00 25-Jun-25 16:00 ALTALINK Outage 413L (239s Castle River - 632s Russell) maintenance 9 Hours
Daily
 
25-Jun-25 07:00 25-Jun-25 17:00 ALTALINK TE 227s Protection & Control (227s Cutting Lake) update relay IP address in line with scada work 10 Hours
Daily
 
25-Jun-25 07:00 26-Jun-25 18:00 ALTALINK Outage 973L (39s Bickerdike - 310p Sundance) Repair broken strands on the 973L conductor between spans 24-25. 1.46 Days
Continuous
 
25-Jun-25 07:30 25-Jun-25 17:30 ALTALINK RB 1201L (520s Bennett - BCH Cranbrook) replacing insulation at STR 2 10 Hours
Daily
 
25-Jun-25 08:00 25-Jun-25 16:00 ALTALINK Outage 864L (397s Benbow - 864AL tap), 864L (864AL tap - 864BL tap), 864L (551s Chevron Kaybob - 864BL tap), 864AL (346s Kaybob - 864L tap), 864BL (355s Chevron Knight - 864L tap), 346s T1 (346s Kaybob), 355s T1 (355s Chevron Knight), 355s T2 (355s Chevron Knight), 551s T1 (551s Chevron Kaybob), 355s 2 (355s Chevron Knight), 355s 4 (355s Chevron Knight), 551s 864N (551s Chevron Kaybob), 346s 864AN (346s Kaybob) close open point 'B' on 346s 4.16kV bus 8 Hours
Daily
 
25-Jun-25 08:00 25-Jun-25 17:00 ALTALINK TE 492s RTU/SCADA (492s Monarch), AltaLink Telecom Equipment 492s Monarch supervisory outage 9 Hours
Daily
 
25-Jun-25 08:00 26-Jun-25 18:00 ENMAX Outage 36.2TR (SS-36) tap changer inspection, reversing switch check, oil sampling MT, TC and tap changer oil filtration maintenance 1.42 Days
Continuous
 
25-Jun-25 08:00 26-Jun-25 17:00 ALTALINK TE 348s RTU/SCADA (348s Marlboro) 2025 MPLS firmware and chassis upgrade at 348S 1.38 Days
Daily
 
25-Jun-25 08:00 25-Jun-25 17:00 ALTALINK TE 15s RTU/SCADA (15s Fort Macleod) remove UF settings from 14L & 41L. 9 Hours
Daily
 
25-Jun-25 08:00 26-Jun-25 16:00 ATCO RB 9L36 (825s Whitefish Lake - 826s Marguerite Lake) repair damaged tower 46 1.33 Days
Continuous
 
25-Jun-25 08:00 26-Jun-25 16:00 ATCO RB 9L37 (825s Whitefish Lake - 826s Marguerite Lake) repair damaged tower 46 1.33 Days
Continuous
 
25-Jun-25 08:00 25-Jun-25 16:00 ENMAX Outage 16.60L (SS-16 - SS-34), 16B69-16.60 (SS-16) breaker maintenance and oil sampling 8 Hours
Continuous
 
25-Jun-25 08:00 25-Jun-25 17:00 ALTALINK TE AltaLink Telecom Equipment upgrade MPLS and lan switch replacement 9 Hours
Daily
 
25-Jun-25 08:30 25-Jun-25 16:30 ALTALINK Outage 356s 552 (356s Milo) 356s552 PRC5 maintenance and counter replacement 8 Hours
Daily
 
25-Jun-25 08:30 25-Jun-25 16:30 ALTALINK, TRANSALTA Outage 59s T1 (59s Peigan) 59s T1 LA replacement 138kV 8 Hours
Daily
 
25-Jun-25 08:30 25-Jun-25 17:00 ALTALINK TE 526s Protection & Control (526s Buffalo Creek) investigate C1 string alarm and potentially replace protection 8.5 Hours
Daily
 
25-Jun-25 09:00 26-Jun-25 14:00 ENMAX Outage 31.3TR (SS-31) grounding improvements and install new surge arrestor insulator supports 29 Hours
Continuous
 
25-Jun-25 09:00 25-Jun-25 18:00 SUNCOR TE 29EDD-34 RTU/SCADA (29EDD-34) RTU power cycle and reboot 9 Hours
Continuous
 
25-Jun-25 10:00 25-Jun-25 17:00 ATCO, CNRL TE 838s RTU/SCADA (838s Horizon Mining) update SMP gateway 7 Hours
Continuous
 
25-Jun-25 10:00 25-Jun-25 12:00 Lethbridge TE Lethbridge PCC replacing RX 1500 network switch at PCC 2 Hours
Continuous
 
25-Jun-25 10:00 26-Jun-25 17:00 ATCO TE 716s Protection & Control (716s Lloydminster), 716s RTU/SCADA (716s Lloydminster) replace the AC cable for 701T cabinet with a larger size conductor 31 Hours
Continuous
 
25-Jun-25 14:00 25-Jun-25 18:00 ATCO RB ATC 793s 144kV Bus (ATC 793s West Peace River) reattach Jumper for 701TCS and open Jumper for 702TCS 4 Hours
Continuous
 
25-Jun-25 16:15 27-Jun-25 16:00 ATCO Outage ATC 793s 702T (ATC 793s West Peace River) complete CCT SW S&C test and maintenance 702TCS 1.99 Days
Continuous
 
26-Jun-25 07:30 26-Jun-25 12:30 ALTALINK Outage 700L (422s Westwood - 746L tap), 700L (746s Sherwood Park - 746L tap), 746L (700L tap - 746AL tap), 422s 700 (422s Westwood), 746s 700N (746s Sherwood Park) replacing insulator on structure 52 5 Hours
Daily
 
26-Jun-25 08:00 01-Jul-25 16:00 SUNCOR Outage 635EDD-1001 635PK-1002 (635EDD-1001), 635EDD-1001 635-752-642 (635EDD-1001), 635EDD-1001 635-752-643 (635EDD-1001) 635EDD-1001 144kV diameter 4 equipment maintenance 5.33 Days
Continuous
 
26-Jun-25 08:00 26-Jun-25 18:00 ATCO TE 927s RTU/SCADA (927s Buchanan Creek), ATCO Telecom Equipment Deadwood_T-Telecom- telecom DC systems outage, load transfer from Hayley charger to unity rectifier
10 Hours
Continuous
 
26-Jun-25 08:00 26-Jun-25 17:00 ALTALINK TE 288s RTU/SCADA (288s Wolf Creek) replace failing SMP16 RTU 9 Hours
Daily
 
26-Jun-25 08:00 26-Jun-25 17:00 ALTALINK TE 534s RTU/SCADA (534s Eckville), 17s RTU/SCADA (17s Benalto), AltaLink PMU, 17s Protection & Control (17s Benalto) upgrade MPLS 9 Hours
Daily
 
26-Jun-25 08:30 26-Jun-25 16:30 ALTALINK Outage 356s 652 (356s Milo) 356s652 PRC5/maintenance/gas top up 8 Hours
Daily
 
26-Jun-25 09:00 26-Jun-25 17:00 ATCO TE 764s RTU/SCADA (764s Heisler) Heisler_S-Telecom - low BES firewall install - outage to local network & SCADA communications 8 Hours
Continuous
 
26-Jun-25 12:31 26-Jun-25 17:30 ALTALINK Outage 706L (410s Josephburg - 706AL tap) replacing insulator on structure 4.98 Hours
Daily
 
27-Jun-25 08:00 03-Jul-25 16:00 ENMAX, ALTALINK Outage 50L (44s Bearspaw Plant - SS-21) HV SW Replacement. 37SW84, 37SW85, 37SW86 6.33 Days
Continuous
 
27-Jun-25 08:00 03-Jul-25 20:00 SUNCOR Outage 29PL6-4 (29EDD-1 Millennium - 30EDD-1) 450501637 - 29EDD1;29CVT-8 SYSTEM;PM 5y 10y (PRC5)
300477553 29PL6-4 A87L GE L90 Firmware 8.6
300512620 29PL6-4 bird cover on line switch 29edd1

6.5 Days
Continuous
 
27-Jun-25 08:00 27-Jun-25 12:00 ENMAX Outage 26.81L (SS-26 - SS-32), 32B138-26.81 (SS-32) HV Breaker SF6 Gas Sample - 32B138-26.81 4 Hours
Continuous
 
27-Jun-25 09:00 05-Jul-25 20:00 SUNCOR Outage 30EDD-1 29PL6-4D1 (30EDD-1) 30EDD-01 - 29PS6-4D1 Replacement TA (Corey) 8.46 Days
Continuous
 
27-Jun-25 12:00 27-Jun-25 18:00 ALTALINK Outage 726L (37s North Calder - 71s Lamoureux) Replacing insulator on structure 197 6 Hours
Daily
 
27-Jun-25 12:00 27-Jun-25 16:00 ENMAX Outage 32.83L (SS-32 - SS-40), 32B138-32.83 (SS-32) HV Breaker SF6 Gas Sample - 32B138-32.83 4 Hours
Continuous
 
27-Jun-25 13:00 27-Jun-25 17:00 ATCO RB ATC 793s 144kV Bus (ATC 793s West Peace River) re-attach jumper for 702TCS at 793s
4 Hours
Continuous
 

Prepared On:   2025-06-18   14:40:24

This document and the information contained herein are based upon information and data which by their nature contain a degree of uncertainty and are subject to change. In addition, this document may contain information and data from public sources and/or third parties, which have been assumed to be accurate and complete and have not been verified. Accordingly, the Independent System Operator, operating as the Alberta Electric System Operator (the "AESO") makes no warranty, representation or guarantee, express or implied, with respect to this document or the information contained herein, including, but not limited to, any warranty, representation or guarantee of accuracy, completeness, timeliness, reliability, availability, absence of computer virus, non- infringement, merchantability or suitability for any purpose. Under no circumstances will the AESO, its members, officers, employees, contractors or agents, or any of their respective affiliates, be liable for any errors or omissions in, or any losses, damages or claims whatsoever, whether in contract, tort or otherwise, arising from use of or reliance upon, this document or any information contained herein.